Real Markham solar estimate

What does a 10kW solar panel installation cost in Markham?

Typical estimate for this project
$26,840.75
Possible Extra
$1,050.00
Your estimate may differ — get a personalized estimate below.

For this Markham 10kW solar install, RenoFiz estimated about $26,841 CAD for the mandatory scope, plus up to $1,050 CAD of possible extra work if brittle shingles or localized roof deck rot turn up during installation.

Estimate my projectView breakdown
Calculate project costs in minutes. We only share your project details with a contractor when you ask to be connected.
Installer wearing a safety harness kneeling on a shingle roof while positioning a solar panel next to a partially completed array
Is this like your project?

Location

Markham, ON (FSA L3R)


Utility

Alectra


System size

10kW grid-tied, no battery


Existing service

100A panel (no upgrade)


Roof

Asphalt shingles, 11-15 years old


Inverter location

Outside, near the meter

Cost breakdown

Where the $26,841 project cost goes

Where the $26,841 project cost goes

See the full cost breakdown for this project.

Scope itemLabourMaterialsTotal
Permit & Utility Administration$399.00$950.00$1,349.00
Structural Engineering Review$1,750.00$1,750.00
Solar Racking & Roof Attachments$1,045.00$2,600.00$3,645.00
Solar Array & Inverter Installation$1,425.00$16,675.00$18,100.00
Electrical Service Integration (100A)$731.50$300.00$1,031.50
Exterior AC Disconnect$266.00$400.00$666.00
Inspection & Commissioning Coordination$299.25$299.25
Complete base project cost$4,165.75$22,675.00$26,840.75
Total Cost

$26,840.75

Possible extra

$1,050.00

On-site decisions or hidden conditions that could increase the scope.
Get an estimate for your solar project

Want an estimate for your project?

Chat with Chris, RenoFiz's AI project assistant. Chris will build a scope, show what could change the price, and connect you with the right pro.

Estimate my projectSee another detailed estimate
Things to know

Things to know for your project

Things to know for your project

Conditions, constraints, and on-site decisions that shape the final project cost.

Brittle shingles at attachment points

Trigger: Shingles crack or fail to lift during flashing installation due to their 11-15 year age.

A general contractor would replace the affected asphalt shingles at the attachment points. This example identifies approximately $450 in possible additional work for this item.


Roof deck rot

Trigger: Soft or decayed wood is identified during racking installation after shingles are removed.

A general contractor would repair the localized roof deck rot. This example identifies approximately $600 in possible additional work for this item.


Keeping the existing roof

Trigger: The homeowner declined replacing the 11-15 year old shingle roof before installing the panels.

If the roof fails while the panels are on it, the panels must be removed and reinstalled around the roof work. The source example does not assign a price to this future scenario.


Choosing a 200A panel upgrade instead

Trigger: The homeowner declined a 200A panel upgrade in favour of a line-side tap or derate on the existing 100A service.

Choosing a full panel upgrade instead of the line-side tap or derate would change the electrical service integration scope and cost.

How the estimate was created

The real conversation behind this estimate

The real conversation behind this estimate

This is the how RenoFiz gathered the facts and turned a simple request into a scoped estimate.

Homeowner

I'd like a 10k solar install on my roof?

RenoFiz

I'd be glad to help scope out a solar project. For a system that size, I'll need a few details about your home and your goals to build an accurate estimate.

Question: What is your Forward Sortation Area (FSA)?

Question: When you say "10k," do you mean a 10kW (kilowatt) capacity system or a $10,000 budget?

  • 10kW Capacity
  • $10,000 Budget

Question: What's your current roof material, and roughly how old is it?

Question: Do you want to include battery storage (like a Tesla Powerwall), or just a grid-tied system?

  • Grid-tied only
  • Grid-tied + Battery Storage
  • Off-grid

Question: Do you know the amperage of your main electrical panel?

  • 100 Amp
  • 200 Amp
  • 400 Amp
  • I'm not sure

Photos that would help A few photos would help confirm your roof and electrical system are solar-ready:

  • Roof Overview: a clear shot of the roof faces where the panels would go.
  • Electrical Panel: an overview of your main breaker panel, plus a close-up of the labels/directory.
  • Utility Meter: your outdoor electric meter and where the power enters the house.
Homeowner

What is your Forward Sortation Area (FSA)?: WHAT IS THIS?

When you say "10k," do you mean a 10kW (kilowatt) capacity system or a $10,000 budget?: 10kW Capacity

What's your current roof material, and roughly how old is it?: Shingles

Do you want to include battery storage (like a Tesla Powerwall), or just a grid-tied system?: Grid-tied only

Do you know the amperage of your main electrical panel?: 100 Amp

RenoFiz

An FSA is simply the first three characters of your Canadian postal code (like M5V or L3R). It tells me your local utility and the permit rules for your area.

I've set your project to 10kW capacity on a 100 Amp panel. One thing to flag: a 10kW system produces a lot of power — usually more than electrical code lets a standard 100 Amp panel carry. We'll most likely need a panel upgrade to make it work.

Question: What are the first three characters of your postal code?

Question: Roughly how old is your shingle roof?

  • 0-5 years
  • 6-10 years
  • 11-15 years
  • 15+ years
  • I'm not sure

Question: Would you like the estimate to include an upgrade to a 200 Amp panel?

  • Yes, include the upgrade
  • No, I want to see if there's another way

Photos that would help If you get a moment, a photo of your electrical panel (door open so I can see the breakers) would really help confirm what's needed for the 10kW connection.

Homeowner

What are the first three characters of your postal code?: L3R

Roughly how old is your shingle roof?: 11-15 years

Would you like the estimate to include an upgrade to a 200 Amp panel?: No, I want to see if there's another way

RenoFiz

Thanks for that. Since you're in Markham (L3R), your utility is Alectra Utilities.

For a 10kW system on a 100 Amp panel, the "other way" usually means a line-side tap (tying the solar in ahead of your main breaker) or derating the main breaker if your home's electrical load allows. I've added those steps to the plan.

The bigger "readiness" issue is the roof. Solar panels are meant to stay up for 25 to 30 years. Your shingles are already 11–15 years old, so they've probably got only 5–10 years left. If the roof fails with panels on it, you'd pay a contractor thousands just to remove and reinstall them around the roof repair.

Question: Since your roof is 11-15 years old, would you like to include a price for stripping and re-shingling it before the solar goes on?

  • Yes, include a roof replacement in the estimate
  • No, I'll take the risk with the current roof

Question: Do you have a preferred spot for the inverter (e.g., in the garage near the panel, or outside on the house)?

  • Inside (Garage/Utility room)
  • Outside (Near the meter)
  • I'm not sure

Photos that would help A photo of your main electrical panel (door open) and the area around your utility meter would help a lot — it lets a contractor see whether a line-side tap is physically possible in your setup.

Homeowner

Since your roof is 11-15 years old, would you like to include a price for stripping and re-shingling it before the solar goes on?: No, I'll take the risk with the current roof

Do you have a preferred spot for the inverter (e.g., in the garage near the panel, or outside on the house)?: Outside (Near the meter)

RenoFiz

Here's the estimate plan

Work Summary

The client wants a 10kW solar install on an 11-15 year old shingle roof. The system is grid-tied with no battery storage, and the inverter mounts outdoors. To skip a full 200A panel upgrade, the tie-in uses a line-side tap or breaker derate on the existing 100A service. Alectra Utilities net-metering coordination is required.

Required Permits

Permit / InspectionOwnerReason
Electrical permitelectricianRequired for all new solar installations and service connections.
Alectra Utilities Net Metering ApplicationelectricianRequired to tie solar into the grid and earn credits in Ontario.

Bill of Process

StepOwnerDescription
BOP-01electricianApply for the electrical and building permits, coordinate the structural review, and file the Alectra Utilities Net Metering application.
BOP-02structural_engineerAssess the roof structure for the solar array load and provide stamped drawings/report.
BOP-03solar_installerInstall roof attachments and the racking system on the existing asphalt shingles.
BOP-04solar_installerMount the 10kW array and install the exterior-rated inverter near the meter.
BOP-05inspectorCarry out the rough-in electrical inspection of DC wiring, grounding, and conduit.
BOP-06electricianPerform the line-side tap or main breaker derate to tie solar into the 100A service without a full panel upgrade.
BOP-07electricianInstall the exterior AC disconnect as required by Alectra Utilities.
BOP-08inspectorCarry out the final electrical and building inspections and coordinate utility commissioning for net metering.

Cost Estimate

TitleDescriptionRange
Permit & Utility AdministrationPrepare and submit the electrical permit application and the Alectra Utilities Net Metering application, and coordinate the utility requirements for the grid-tie connection.$1,045 - $1,645
Structural Engineering ReviewStructural assessment of the existing roof framing to confirm load-bearing capacity for the array, with a stamped engineering report for building-permit compliance.$1,400 - $2,100
Solar Racking & Roof AttachmentsInstall roof attachments and the racking system for the 10kW array, flashing every penetration on the existing asphalt shingles.$2,855 - $4,435
Solar Array & Inverter InstallationMount the 10kW array and install an exterior-rated string inverter near the utility meter, including DC string wiring and grounding.$14,440 - $21,810
Electrical Service Integration (100A)Perform a line-side tap or main breaker derate to fold the solar feed into the existing 100A service panel, including labeling and circuit protection.$790 - $1,285
Exterior AC DisconnectInstall an exterior-rated AC disconnect between the inverter and service panel as required by Alectra Utilities safety standards.$495 - $845
Inspection & Commissioning CoordinationCoordinate and attend the final electrical inspection, and manage the utility commissioning for Net Metering activation.$220 - $370

Cost Breakdown

CategoryAmount
Materials$18,100 - $27,300
Labour$3,280 - $5,015
Total$21,375 - $32,215

Potential Additional Items

DescriptionTradeEst. CostOn-Site Trigger
Replacement of brittle asphalt shingles at attachment points if the existing roof won't reseal.General Contractor$350 - $550Shingles crack or won't lift during flashing due to age (11-15 years).
Repair of localized roof deck rot found after pulling shingles for attachments.General Contractor$450 - $750Soft or decayed wood found during racking installation.

The Request a Pro button is now active — tap it to connect with a local contractor for an on-site visit and firm quote.

Related projects

View Other Estimates

View Other Estimates

See other projects in Markham or in related trades.

Electrical
Markham, ON
Service upgrade
What does a 200-amp electrical panel upgrade cost in Markham?

A homeowner wants a licensed electrician to upgrade an overhead service to 200 amps, swap the exterior mast and meter base, and fit a new main breaker panel in the garage. RenoFiz scopes Alectra Utilities coordination, service demo, new service equipment, grounding/bonding, permit, and inspection coordination.

View project cost details